Gubrist gets third tube
Our geodata are continuously being updated. The «Third tube of Gubrist Tunnel» project is now complete and the changes are already visible on our online maps.
17.04.2023 | DKW


After six years of construction, the third tube of the Gubrist Tunnel was opened on April 15.
In future, all traffic in the direction of Bern/Basel will run through the new, three-lane tunnel. The existing two tubes take traffic in the opposite direction. The additional construction is intended to alleviate the traffic situation at the Gubrist Tunnel. An exceptional construction: there is no other tunnel in Switzerland with a diameter of almost 16 metres!
The changes can now be seen on our online maps.
Further information